Punjab PWD (B&R) ยท SBD dated 12-12-2025

Punjab PWD SBD Helper: Clauses, LD, Security & Calculators

The Standard Bidding Document for regular PWD (B&R) works explained in plain words, with the clause and page number for every answer. Search a topic, or use the calculators for milestones, liquidated damages, bid capacity, securities, price adjustment and more.

Checked against the Punjab PWD (B&R) Standard Bidding Document dated 12-12-2025 ยท Page last updated 15 Nov 2026

Before you rely on a number: page numbers are the printed page numbers of the SBD (12-12-2025). Items left blank in the SBD, such as the completion period, the Defect Liability Period (DLP) and the liquid-asset figure, come from the Contract Data and BDS of your own tender. Always check the agreement for your work.

Whole tender procedure: from filling the bid to award and agreement

Every step in order, with what to do, the time limit and the clause. To get your own dates, use the tender timeline calculator.

1. Get ready on the portalEnrol on eproc.punjab.gov.in with your own Digital Signature Certificate (DSC). Keep your PWD enlistment, PAN, GST and EPF registration valid. (IFB 3โ€“4, p. 6; ITB 4.2, p. 14)
2. Read the NIT and download the documentsThe NIT gives the work, estimated cost, EMD, tender fee, completion period and dates. Download the bid documents only from the portal; tampering with them means 6 months' debarment. Keep checking for addenda and corrigenda until the last date. (IFB 1โ€“5, pp. 5โ€“6; ITB 10)
3. Check that you are eligibleUp to Rs 10 crore: valid PWD enlistment in the right class and category. Above Rs 10 crore: turnover, similar works, liquid assets, bid capacity (use calculators 4โ€“6). JVs and consortia are not allowed unless the BDS allows them. You can be disqualified for false information or a poor record (abandoned works, long delays, litigation). (ITB 3, 4, pp. 13โ€“17)
4. Visit the siteNot compulsory but strongly advised, at your own cost. You are taken to have priced every risk you could have seen; nothing extra is paid for a misunderstanding. (ITB 6โ€“7, p. 17)
5. Ask questions in timeSend queries to the Engineer in writing so they reach him more than 7 days before the bid deadline. For a pre-bid meeting, send them 3 days before the meeting. Answers and changes come as corrigenda. (ITB 9, pp. 18โ€“19)
6. Prepare the Technical Bid (Envelope I)Scanned, digitally signed: qualification information and supporting documents, the certificates and affidavits (not blacklisted, information true), PAN, GST, EPF, bid capacity details with an undertaking, an undertaking that the bid stays valid for the BDS period, and, for lump-sum works, general arrangement drawings. Above Rs 10 crore, also: constitution / power of attorney, similar-work certificates, equipment, key staff, 5 years' audited accounts, a bank credit-line letter (10%, not over 3 months old), the 25% cash undertaking and bank references. Do not upload the SBD itself; only agree to it online. (ITB 4.2, 12.1, pp. 14, 19; IFB 9, 11)
7. Prepare the Financial Bid (Envelope II)In the Form of Bid: percentage at par / above / below (percentage-rate tender), the rate for every item in figures and words (item-rate), or one lump sum. Rates include all taxes and risks. An item left without a rate is not paid. No conditions: conditional bids are rejected. (ITB 12.1, 13, 17, pp. 19โ€“22)
8. Pay the tender fee and EMD onlineBoth through net banking / NEFT / RTGS on the portal. A bid without an acceptable EMD is rejected. (IFB 6โ€“7, p. 6; ITB 16.2, p. 21)
9. Submit before the deadlineUpload both envelopes, digitally signed, before the last date and time by the server clock; the system takes no late bids. If the last date becomes a holiday, the next working day applies. Only one bid per work: more than one disqualifies all of them. Once submitted, a bid cannot be resubmitted or withdrawn, and withdrawing or modifying during validity forfeits the EMD. (IFB 8, 13; ITB 5, 16.5, 19โ€“21, pp. 17โ€“22)
10. Technical bid openingOpened online on the date in the NIT; bidders may attend. (IFB 12; ITB 22.1โ€“22.2, p. 23)
11. Clarifications and the technical evaluationFor rectifiable defects the department writes to you, usually within 10 days of opening. Reply within 7 days; the letter also gives the financial-bid opening date. The evaluation is to be finished within 21 working days, and the list of responsive bidders is drawn up. Do not contact the Engineer about your bid otherwise; trying to influence him can get the bid rejected. (ITB 22.3, 24, pp. 23โ€“24)
12. Financial bid openingOnly the responsive bidders' financial bids are opened. Names, prices and discounts are read out and minuted; anything not read out is not considered. (ITB 22.4โ€“22.5, p. 23)
13. Financial evaluationOnly substantially responsive bids, without material deviations, are compared. The price-adjustment effect is ignored. If the lowest bid is more than 25% away from the estimate, a price analysis and an additional performance security may be asked for. (ITB 25โ€“26, pp. 24โ€“25)
14. AwardThe competent authority awards to the substantially responsive bidder with the lowest evaluated bid price. It may also reject any or all bids before award without giving reasons. The Letter of Acceptance (LoA) is sent before the bid validity (120 days) expires; it forms the contract, subject to the PS. (ITB 27โ€“29, p. 25; Form of Bid, p. 111)
15. After the LoAGive the performance security (5%) within 21 days; bring the originals of the uploaded documents for verification; sign the agreement within 28 days; submit the programme within 21 days; start the work within 10 days of the allotment letter. Failing to give the PS or sign the agreement means the award is cancelled and the EMD forfeited. (ITB 29โ€“30, pp. 25โ€“26; IFB 10; GCC 26, 46)
16. Unsuccessful biddersThey are informed once the PS is received, and their EMD is returned within 28 days after the bid validity ends. (ITB 16.3, 29.4, pp. 21, 25)

Get your own dates for every step with the tender timeline calculator.

When money is paid, and when it can be deducted

Every payment to the contractor and every deduction the SBD allows, with when it happens and the clause. To work out a running bill, use calculator 12.

Money paid to the contractor

PaymentWhenConditionsClause
Mobilisation advance (up to 5%, excluding maintenance)After the agreement, on requestUnconditional BG of the same amount; used only for equipment, plant and mobilisation; 9% interest a yearGCC 47.1โ€“47.2, p. 72
Running billMonthly; the Engineer checks it within 30 daysBill on the printed form with measurements, QC test reports and instruction-book copies; contractor signs any correctionsGCC 39.1โ€“39.2, 40.1, pp. 68โ€“69
Secured advance (up to 75% of material value)With the monthly billNon-perishable, as per specification, at site, stored in measurable stacks, ownership shown, indemnity bond, not excessiveGCC 48.1, p. 73
Variations and extra itemsIn the running billsItem rate: quotation within 7 days of the Engineer's request. Lump sum: per Schedule S-IIGCC 38.1, p. 66; 37, p. 68; S-II, p. 117
Compensation eventsIn the running billsMust be claimed in the bills; claims not included are treated as waivedGCC 39.4, 41, pp. 69โ€“70
Price adjustment (bitumen, cement, steel)Monthly, with the billNot in the first 6 months (except bitumen in road works); lower price in extended time; no profitGCC 44, p. 71; CD pp. 85โ€“86
Refund of LDNext payment certificate after EOT is grantedThe completion date is extended after LD was paidGCC 46.4, p. 72
Refund of the deposit-at-call (arbitration)After the awardIn proportion to the amount awarded in the claimant's favourGCC 25, p. 61
Final paymentWithin 56 days of a correct and complete final accountAfter the completion certificateGCC 53, p. 74
Retention: first 50%3 months after completionEngineer certifies defects removed; final measurements recordedGCC 45.2, p. 71
Retention: balance 50%After 1 year or the end of the DLP, whichever is laterAll notified defects correctedGCC 45.3, p. 71
Performance security released28 days after the DLP endsValidity ends then; extra PS for an unbalanced bid: 28 days after the completion certificateGCC 49, p. 73
EMD of an unsuccessful bidderWithin 28 days after the bid validity endsThe successful bidder's EMD stays in the retentionITB 16.3โ€“16.4, p. 21

Money deducted or held back

DeductionWhenHow muchClause
Retention (security deposit)From every bill until completion5% of each payment; the EMD counts towards itGCC 45.1, p. 71
Mobilisation advance recoveryFrom the running billsIn proportion to the work completed, plus 9% interest a year; the BG reduces as the advance is repaidGCC 47.1, 47.3, p. 72
Secured advance adjustmentWhen the material is used in the workThe advance paid on that material is taken backGCC 39.2, 48, pp. 69, 73
Taxes at source (income tax TDS, GST TDS, cess, etc.)From every billAs per the law in force; rates are inclusive of taxesGCC 39.2, 42.1, pp. 69โ€“70
Liquidated damagesLate start (after 10 days), a missed milestone, late completionUp to 1% of the contract amount a week, maximum 5%GCC 46, pp. 71โ€“72
Programme not updatedFrom the next payment certificateThe amount in the Contract Data, held until the updated programme is givenGCC 26.3, p. 62
Third-party techno-financial auditWorks of Rs 1 crore and aboveAt the rate in the Department of Finance letters, on the total cost of workGCC 31.2, p. 64
Defect not correctedAfter the time given in the defect noticeTwice the assessed cost of correcting itGCC 34.1, p. 65
As-built drawings / manuals not givenFrom the payments due (final bill)Rs 10,000 or 1% of the contract amount, whichever is higher; due 15 days after completionGCC 54.2, p. 74; CD p. 86
Insurance premium paid by the EmployerIf the contractor fails to insureThe premium paidGCC 13, p. 58
Labour law defaults, unpaid wages, finesWhen the Employer has to pay themThe amount paid; can also come from the PSGCC 10.3, p. 56; Labour Regulations, pp. 103โ€“108
Excess payment or dues on any other contractAny timeFrom any sum payable under this or any other contract with the GovernmentGCC 40.3, p. 69
Earlier certified itemsIn a later certificateThe Engineer may exclude or reduce them in light of later informationGCC 39.5, p. 69
Compensation on terminationOn termination for the contractor's breach5% of the contract value; LD + compensation maximum 7.5%GCC 56.1, p. 75
EMD forfeitedBid withdrawn, or the agreement or PS not givenThe full EMDITB 16, p. 22

Running payments are only advances against the final payment; they are not acceptance of the work (GCC 40.5). Items with no rate entered are not paid (GCC 40.2).

Calculators

Pick a calculator. Each one shows the working step by step, has a Fill example button, a Download PDF button and a Know in detail guide in plain words.

๐Ÿ“ Your contract details: fill once, used in every calculator

Your entries in every calculator are saved only on this device, so you can come back later.

13. Tender timeline

Your own dates from the NIT: IFB; ITB 9, 15, 16, 22, 29, 30
Know in detail

How the dates are worked out

  • Clarification requests must reach the Engineer more than 7 days before the deadline, so the last safe day is 8 days before.
  • Pre-bid queries: 3 days before the meeting.
  • Technical evaluation: within 21 working days of opening. Saturdays and Sundays are skipped here; gazetted holidays are not, so the real date may be a few days later.
  • Clarification letter: usually within 10 days of opening; your reply within 7 days of the letter.
  • Bid validity counts from the submission deadline; the LoA must come before it ends.
  • EMD of unsuccessful bidders: within 28 days after validity ends.

Tip

  • Upload a day early: the portal goes by its own server clock, and the department is not responsible for network problems (IFB 8).

1. Key dates and milestones

From the allotment letter (LoA). ITB 29โ€“30; GCC 26, 33, 45, 46, 49
Know in detail

What the SBD says

  • Performance security (5%) within 21 days of the LoA (ITB 30).
  • Agreement signed within 28 days of the award (ITB 29.3).
  • Work programme to the Engineer within 21 days (GCC 26.1).
  • Work must start within 10 days of the acceptance letter, otherwise LD can be charged (GCC 46.1).
  • Milestones: 10% of work at 25% of time, 30% at 50%, 65% at 75%, 100% at 100% (GCC 46.1).
  • Half the retention is refunded 3 months after completion; the rest after 1 year or the end of the DLP, whichever is later (GCC 45).
  • The PS must stay valid until 28 days after the DLP ends (GCC 49).

Worked example

LoA 1 April 2026, 12 months, DLP 5 years. Start by 11 Apr 2026; PS and programme by 22 Apr; agreement by 29 Apr; milestones on 1 Jul 2026 (10%), 1 Oct 2026 (30%), 1 Jan 2027 (65%); completion 1 Apr 2027; DLP ends 1 Apr 2032; PS valid till 29 Apr 2032.

Common mistakes

  • Counting time from the agreement date: the Contract Data makes the allotment letter the start date.
  • Letting the bank guarantee for the PS expire at completion: it must cover the DLP plus 28 days.
  • Forgetting that the DLP is extended while defects are not corrected (GCC 33).

2. Liquidated damages (LD)

GCC 46: up to 1% of contract amount per week, maximum 5% of contract value
Delay: enter dates, or weeks directly
Know in detail

When LD applies (GCC 46.1)

  • Work not started within 10 days of the acceptance letter.
  • A milestone (10/30/65% of work at 25/50/75% of time) is missed.
  • The whole work is not completed in time.

How much

  • Up to 1% of the contract amount for each week of delay.
  • The rate can be raised each time, up to 1% a week, but the total LD cannot be more than 5% of the contract value (46.2).
  • The SE can reduce LD (46.3). If time is later extended, LD already taken is refunded (46.4).
  • If part of the work is taken over, LD is reduced in proportion (46.6).
  • Once LD reaches the maximum, the Employer can terminate the contract (GCC 55).

Worked example

Contract Rs 2.50 crore, 6 weeks late at 1%: 1% ร— 2,50,00,000 = Rs 2,50,000 a week ร— 6 = Rs 15,00,000. Cap 5% = Rs 12,50,000. LD chargeable = Rs 12,50,000.

Tips for contractors

  • Apply for EOT within 30 days of each hindrance (GCC 27.1). Approved EOT means LD for that period is refunded.
  • Keep a hindrance register signed by the JE/SDO; it is your proof.
  • A part week is usually counted as a full week. Check the order.

3. Milestone progress check

GCC 46.1: 10% work at 25% time, 30% at 50%, 65% at 75%, 100% at 100%
Know in detail

The rule

  • By 25% of the time: at least 10% of the work (by value).
  • By 50%: 30%. By 75%: 65%. By 100%: the whole work.
  • Missing a milestone allows LD of up to 1% a week (GCC 46.1), even though the final date has not come.

Where to get the figures

  • Start date: the allotment letter date.
  • Work done: the gross value of measured work in the running bills (before deductions).

Worked example

Rs 2 crore work, 12 months from 1 Apr 2026. On 1 Oct 2026 (50% of time) work done is Rs 48 lakh = 24%. Required 30% = Rs 60 lakh. Shortfall Rs 12 lakh (6%). The milestone is missed.

Tip

  • If the delay was due to the department (site, drawings, payment), apply for EOT for the milestone as well, with the hindrance record.

4. Bid capacity

ITB 4.4: Assessed bid capacity = A ร— N ร— 2 โˆ’ B; values updated at 8% a year (BDS)
Works done each financial year (Rs, as per CA certificate)
B: works in hand, value still to be done in the next N months (Rs)
Know in detail

The formula (ITB 4.4)

  • A = the highest value of civil works done in any one financial year of the last 5 years, updated to the bid year at 8% a year.
  • N = the time for completion of this work, in years (18 months = 1.5).
  • B = the value of existing commitments and ongoing works still to be done during the next N months (also updated).
  • Bid capacity = A ร— N ร— 2 โˆ’ B. It must be at least the estimated cost.

Where to get the figures

  • Yearly work values: a turnover certificate from a CA, or certificates from the engineers in charge.
  • B: for each work in hand, the balance value that falls within the next N months as per its programme.

How the 8% updating is done here

  • Each FY value is multiplied by 1 + 8% ร— the years from the end of that FY (31 March) to the bid date. Ask the department if they count only whole years; this calculator shows the factor so you can check.

Worked example

Best year Rs 8 crore, updated to Rs 8.64 crore. N = 18 months = 1.5. A ร— N ร— 2 = 8.64 ร— 1.5 ร— 2 = Rs 25.92 crore. B = Rs 5 crore. Bid capacity = Rs 20.92 crore.

5. Update a past value at 8%

BDS (ITB 4): past turnover and work values updated at 8% simple a year
Know in detail

Why update?

  • Old values are brought to today's prices so they can be compared with the estimated cost. The BDS fixes 8% a year, simple (not compound).
  • Updated value = Value ร— (1 + 0.08 ร— years).

Worked example

Rs 5 crore work completed on 31 Mar 2024, bid on 31 Mar 2026: 2 years. 5 ร— (1 + 0.16) = Rs 5.80 crore.

Note

  • Some offices count whole years only. The calculator shows both the exact and the whole-year figure.

6. Eligibility check (works above Rs 10 crore)

ITB 4.2 B and 4.3 B: turnover, similar works, liquid assets, bid capacity
Turnover, last 3 financial years (Rs, before updating)
Similar works completed in the last 5 years
Know in detail

Tests for works above Rs 10 crore

  • Turnover: at least 40% of the estimated cost in any one of the last 3 FYs (updated at 8%).
  • Similar works in the last 5 years (updated): one work of 80%, or two of 50% each, or three of 40% each of the estimated cost.
  • Liquid assets / credit lines: the amount given in the BDS (about 3 months' peak cash flow), with an undertaking to invest 25% in cash and credit lines of 10% (ITB 4.2 B(f)).
  • Bid capacity at least the estimated cost (use calculator 4).

Works up to Rs 10 crore

  • Only valid PWD enlistment in the right class is needed (ITB 4.2 A / 4.3 A).

Common mistakes

  • Using a work that is not "similar" as defined in the NIT.
  • Counting a work completed more than 5 years before the bid date.
  • Adding up two smaller works to make one 80% work: it doesn't count.

7. Securities, retention and advances

ITB 16, 30; GCC 45, 47, 48
Know in detail

Performance security (ITB 30, GCC 49)

  • 5% of the contract price within 21 days of the LoA, as a bank guarantee or FDR, valid until 28 days after the DLP.
  • An extra PS may be asked for if the bid is unbalanced, more than 25% below the estimate (ITB 26.4).

Retention (GCC 45)

  • 5% is deducted from each bill until 5% of the contract price is held. The EMD counts towards it.
  • 50% is refunded 3 months after completion; the rest after 1 year or the end of the DLP (whichever is later), once defects are corrected.

Mobilisation advance (GCC 47)

  • Up to 5% of the contract price excluding maintenance, against a bank guarantee of the same amount.
  • Interest at 9% a year, recovered from the bills with the advance.

Secured advance (GCC 48)

  • Up to 75% of the value of non-perishable materials brought to site for the work; recovered as the material is used.

Worked example

Contract Rs 2.50 crore: PS Rs 12.50 lakh. Retention to be held Rs 12.50 lakh; EMD Rs 5 lakh already counts, so Rs 7.50 lakh more is taken from bills. Mobilisation advance up to Rs 12.50 lakh; if Rs 10 lakh is outstanding for 6 months, interest = 10,00,000 ร— 9% ร— 6/12 = Rs 45,000.

8. Price adjustment: bitumen, cement, steel (month by month)

GCC 44 with the Contract Data formulas. One row per month; no contractor's profit on PA
What each box means and where to get the figure

Bitumen

  • B0: the official retail price of bitumen at the Indian Oil (IOC) depot, Panipat, taken by the Department when it approved the bids. It is printed in your Contract Data (item 44).
  • Bi: the official IOC Panipat retail price for the month. Take it from the IOC price circular for that month; your division office keeps these. If the price changed within the month, make two rows.
  • Pb: the bitumen actually consumed in the work done that month, in MT.

Cement

  • Rc: the cement rate per 50 kg bag taken by the Department while inviting bids, with the date it was fixed as a CSR rate. Both are printed in your Contract Data.
  • C0: the All India Wholesale Price Index (WPI) for cement on the date Rc was fixed. It is an index number such as 127.7, not rupees. Enter the rate date and press Fill automatically.
  • Ci: the same index for the month of work.
  • Nc: the number of 50 kg bags actually consumed that month.

Steel

  • Rs: the steel rate per MT taken by the Department while inviting bids, with its date (Contract Data).
  • S0 and Si: the WPI for steel on the rate date and for the month of work. Index numbers, filled automatically.
  • Qs: the steel actually consumed that month, in MT.

Dates

  • Date of allotment: the date of allotment of the work. The first six months are counted from it.
  • Original completion date: the intended completion date. Work after it is extended time.
  • Price on the original completion date: for extended time the lower of this and the month's figure is used.
The WPI is published every month by the Office of the Economic Adviser, Government of India (eaindustry.nic.in). The SBD says only โ€œWholesale Price Index for cementโ€ and โ€œfor steelโ€; it does not name the exact line. Confirm the line with your division.
1Choose the material
Amount = bitumen used ร— (IOC price this month โˆ’ base price)
In the SBD: Vb = Pb ร— (Bi โˆ’ B0)
2Fill these from your Contract Data
Take B0 and every month's price from the same column of the IOC price list (Basic, or Total with GST), for the same grade and supply point. Do not mix them. The SBD does not say which column; follow the basis of B0 in your Contract Data.
More options (most users can skip these)
3Add each month of work
MonthPb: bitumen used (MT)Bi: price for the month (Rs/MT)
Know in detail

When PA is paid (GCC 44)

  • For bitumen, cement and steel only, up or down with the market.
  • Nothing is adjusted for work done in the first 6 months from the date of allotment. The only exception is bitumen in road works, which is adjusted from the start. In building works there is no exception.
  • PA runs up to the intended completion date, or up to an extension granted by the Engineer. For work done in the extended time, the lower of the price on the intended completion date and the price for the month is used.
  • Work executed under variations is left out; its rates are settled separately.
  • No contractor's profit is added to PA.

Where to get the figures

  • Bitumen: B0 is the IOC Panipat depot retail price printed in the Contract Data; Bi is the IOC Panipat price for the month. If the price changed within the month, split the month.
  • Cement / steel: C0/S0 and Ci/Si are the All India Wholesale Price Index: C0/S0 on the date the rate Rc/Rs was fixed, Ci/Si for the month of work. Rc / Rs are the Department's rates printed in the Contract Data.
  • Quantity: the quantity actually consumed in the work that month.

Worked example (cement)

1,000 bags used, Rc Rs 400, C0 137.4 (index on the rate date), Ci 130.2 (index for the month): Vc = 1000 ร— 400 ร— (130.2 โˆ’ 137.4)/137.4 = โˆ’Rs 20,961, recoverable.

9. Quantity variation and extra time

GCC 36: rate review when the quantity varies by more than 25% and the change is more than 1% of the ICP
Know in detail

The rule (GCC 36)

  • The rate can be revised only if both are true: the final quantity differs from the BOQ by more than 25%, and the change is worth more than 1% of the Initial Contract Price.
  • The revised rate applies only to the quantity beyond 125% (or the shortfall below 75%). Up to 25% the BOQ rate applies.
  • Without the Employer's approval, the total cannot exceed the ICP by more than 15%.
  • Extra or changed work gets extra time in proportion to its value (GCC 36.1).
  • For a variation the Engineer asks for, quote within 7 days (GCC 38.1).

Worked example

BOQ 1,000 cum at Rs 500; actual 1,400 cum (+40%). Change 400 ร— 500 = Rs 2,00,000. With ICP Rs 1.5 crore that is 1.33%: both tests met. 1,250 cum at Rs 500; 150 cum at the revised rate.

10. Payment on termination (contractor's breach)

GCC 56.1: work done less advances, recoveries, TDS and 5% compensation; LD + compensation capped at 7.5%
Know in detail

When this applies

  • The contract is terminated for a fundamental breach by the contractor, after 14 days' notice (GCC 55). Examples: work stopped for 28 days, delay reaching the maximum LD, a defect not corrected, the security not kept valid, corrupt practice.

The certificate (GCC 56.1)

  • Value of work done โˆ’ advances received โˆ’ other recoveries โˆ’ TDS โˆ’ 5% of the contract value as compensation.
  • LD + compensation together cannot exceed 7.5% of the contract value, or the amount available with the Engineer (retention, PS and dues), whichever is less.
  • If the result is negative, the balance is recovered by encashing the PS.

Worked example

Contract Rs 2.50 crore; work done Rs 1.20 crore; paid Rs 90 lakh; LD already Rs 10 lakh. The cap is 7.5% = Rs 18.75 lakh, so only Rs 8.75 lakh of the Rs 12.50 lakh compensation can be taken. Net = 1,20,00,000 โˆ’ 90,00,000 โˆ’ 8,75,000 = Rs 21,25,000.

11. Dispute and arbitration deadlines

GCC 25: the Engineer's decision, arbitration and the forum
Know in detail

The steps (GCC 25)

  • Refer the dispute to the Engineer in writing. He decides within 60 days.
  • If not satisfied, give notice for arbitration within 60 days of the decision.
  • The reference must be made within 120 days of the claim arising (6 months for final-bill matters), otherwise the claim may be barred.
  • Deposit at call of 10% of the amount claimed with the reference.
  • The award is to be given within 6 months.

Who is the arbitrator

  • Claim up to Rs 5 crore: the Superintending Engineer of the circle.
  • Rs 5 to 15 crore: another SE appointed by the Employer.
  • Above Rs 15 crore: a 3-member tribunal.

Tips

  • Keep proof of delivery of every letter; the deadlines run from the dates.
  • Raise every claim in the running bills too: claims left out of the bills are treated as waived (GCC 39.4).

12. Running bill: what is paid and what is deducted

GCC 39.2, 42, 44, 45, 46, 47, 48: the net cheque for a running bill
Contract
This bill
Advances
Taxes (as per current law)
Other deductions this bill (Rs)
Know in detail

How a running bill is passed (GCC 39)

  • Each month the contractor submits a bill on the printed form with the measurements, the quality-control test reports and copies of the instruction book.
  • The Engineer checks it within 30 days and certifies the amount after deducting advances, retention, other recoveries and taxes at source. The contractor signs the corrections before payment.
  • Include every claim (variations, compensation events) in the bills. Claims left out are treated as waived (39.4).

How this calculator works

  • Retention: 5% of the total gross value so far, less what is already held (EMD + earlier retention). So the EMD is used up first.
  • Mobilisation advance: recovered in proportion to the work done (this bill รท contract amount ร— advance), never more than the balance, plus 9% a year interest on the balance for the months entered (GCC 47).
  • Secured advance: up to 75% of the material at site is paid; the advance on material now built into the work is taken back.
  • Taxes: enter the rates in force on the bill date. The calculator applies them to the gross value of work. Your office may use a different base; check with the accounts branch.

Common mistakes

  • Taking retention again on the EMD part: the EMD is part of the 5%.
  • Recovering the whole mobilisation advance from the first bills: the SBD says proportionate recovery.
  • Forgetting to claim price adjustment every month.

FAQ: simple questions, tricky answers

Questions that look easy but are often answered wrongly at site and in the office. Each answer is from the SBD, with the clause.

Is retention money the same as the performance security?
No. They are two separate securities held at the same time. The performance security is a separate 5% bank guarantee or FDR, given within 21 days of the LoA and valid until 28 days after the DLP. Retention is 5% cut from every bill (the EMD counts towards it) and refunded in two halves after completion. ITB 30; GCC 45, 49
Can LD ever be more than 5%?
LD alone, no: it is capped at 5% of the contract value. But if the contract is terminated for your breach, a further 5% compensation is taken, and LD plus compensation can together reach 7.5% of the contract value. GCC 46.2, 56.1
If I get an extension of time later, do I get back the LD already deducted?
Yes. If the completion date is extended after LD was paid, the Engineer corrects the overpayment in the next payment certificate. GCC 46.4
I missed a milestone but caught up later. Is the LD refunded automatically?
Not automatically. The SBD refunds LD only when the completion date is extended. Otherwise, make a representation to the SE, who can reduce LD by a written speaking order. GCC 46.3, 46.4
A BOQ quantity went up by 30%. Do I automatically get a new rate?
Not always. Two conditions must both be met: the change is more than 25% of the BOQ quantity, and it is worth more than 1% of the Initial Contract Price. Even then, the new rate applies only to the quantity beyond 125%. GCC 36
My DLP is 5 years. Do I get the second half of the retention after 1 year?
No: after 5 years. The balance is refunded after 1 year or the end of the DLP, whichever is later, and only once all notified defects are corrected. GCC 45.3
The first 50% of retention comes back 3 months after completion. Is that automatic?
No. The Engineer must certify that defects are removed and the final measurements must be recorded. It is 50% of the total retained amount. GCC 45.2
Is the winning bidder's EMD returned like the others?
No. It is not returned separately; it is adjusted in the retention money. ITB 16.4
Can price adjustment reduce my payment?
Yes. The formulas work both ways: if bitumen, cement or steel prices fall below the base, the difference is recovered. GCC 44; CD pp. 85โ€“86
Do I get price adjustment from the first month?
Only for bitumen in road works. For everything else there is no adjustment in the first 6 months from the allotment letter. GCC 44
Is profit added on price adjustment?
No. The Contract Data says the contractor's profit is not considered on price adjustment. CD pp. 85โ€“86
Are the 21 days for the performance security working days?
No, calendar days. In this SBD, days are calendar days unless a clause says working days. GCC 1.1; ITB 30.1
Can I start the work before the agreement is signed?
Yes, and you must. The LoA itself forms the contract (subject to the PS), and the start date is the allotment letter date. You must start within 10 days, even though the agreement may be signed up to 28 days after the award. ITB 29.2โ€“29.3; GCC 46.1; CD p. 83
I forgot to claim an extra item in the RA bills. Can I add it in the final bill?
Risky. Claims not included in the bills or statements are treated as waived. Claim variations and compensation events in the running bills as soon as they arise. GCC 39.4
My RA bill was passed. Does that mean the work is accepted?
No. Running payments are only advances against the final bill. Defective work can still be ordered out, and items certified earlier can be reduced later. GCC 39.5, 40.5
The drawing and the BOQ say different things. Which one prevails?
The drawing. The order of priority is Agreement, LoA, Contract Data, Conditions, Specifications, Drawings, BOQ, then your Bid. So specifications prevail over drawings, and drawings over the BOQ. GCC 2.3
Can I write 'subject to escalation' or another condition in my bid?
No. Conditional bids are not considered and are rejected. IFB 14; ITB 17.1
Can I give the performance security in cash or by cheque?
No. Only as a bank guarantee in the Section 10 form, or as an FDR as stated in the BDS. ITB 30.1
Who decides my EOT: the Executive Engineer or the SE?
The SE decides, but you must apply to the Engineer (the EE). An application sent to the SDO or any other officer is not considered. GCC 27.1
Is the arbitrator someone outside the department?
Not for most claims. Up to Rs 5 crore, the arbitrator is the SE of the circle; from Rs 5 to 15 crore, another SE appointed by the Employer; only above Rs 15 crore is there a 3-member tribunal. GCC 25
Can the department recover money I owe on a different work from this bill?
Yes. Any sum due to the Government under this or any other contract can be deducted from any amount payable to you. GCC 40.3
Is interest paid on my EMD or retention money?
No. The SBD has no provision for interest on the EMD or the retention. ITB 16; GCC 45
Does the secured advance carry interest like the mobilisation advance?
No, unless you default. The mobilisation advance carries 9% a year. The secured advance is interest-free, but on default the whole balance becomes payable at once with 12% a year interest. GCC 47.1, 48; Section 10, pp. 124โ€“125
Is the DLP counted from the start date or the completion date?
From the completion date, as certified by the Engineer. GCC 1.1; CD p. 83
My bid is 26% below the estimate. Is there any catch?
Possibly. A bid more than 25% away from the estimate can be asked for a detailed price analysis, and an additional performance security may be taken. ITB 26.4
The site was handed over late. Will I be paid for the idle time?
Not under GCC 22.1: late site possession is a compensation event for time extension only. GCC 22.1
Can I sublet 30% of the work with the EE's permission?
No. Sub-contracting is limited to 25% of the contract value, even with approval. GCC 7.1
A defect was not corrected and repair is assessed at Rs 50,000. How much will be recovered?
Rs 1,00,000: twice the assessed cost of correcting the defect. GCC 34.1
If I don't give the as-built drawings, how much is held back?
Rs 10,000 or 1% of the contract amount, whichever is higher. For a Rs 2 crore work that is Rs 2,00,000. GCC 54.2; CD p. 86
If my enlistment is valid on the bid date but expires soon after, is that okay?
For bidding, the bid must meet the criteria on the date bids are received, so it must be valid then. Keep it valid afterwards too, because the department verifies the originals before signing the agreement. IFB 10, 14; ITB 4.2 A

Didn't find your question? Ask here

Send your question about the Punjab PWD SBD. We read every question and add the useful ones to this page.

Related guides

Based on the Standard Bidding Document for Procurement of Works, Government of Punjab, PWD (B&R) Branch, dated 12-12-2025. This is a study aid, not the contract. Where this page and your agreement differ, the agreement prevails.