Punjab PWD SBD Helper: Clauses, LD, Security & Calculators
The Standard Bidding Document for regular PWD (B&R) works explained in plain words, with the clause and page number for every answer. Search a topic, or use the calculators for milestones, liquidated damages, bid capacity, securities, price adjustment and more.
Checked against the Punjab PWD (B&R) Standard Bidding Document dated 12-12-2025 ยท Page last updated 15 Nov 2026
Whole tender procedure: from filling the bid to award and agreement
Every step in order, with what to do, the time limit and the clause. To get your own dates, use the tender timeline calculator.
Get your own dates for every step with the tender timeline calculator.
When money is paid, and when it can be deducted
Every payment to the contractor and every deduction the SBD allows, with when it happens and the clause. To work out a running bill, use calculator 12.
Money paid to the contractor
| Payment | When | Conditions | Clause |
|---|---|---|---|
| Mobilisation advance (up to 5%, excluding maintenance) | After the agreement, on request | Unconditional BG of the same amount; used only for equipment, plant and mobilisation; 9% interest a year | GCC 47.1โ47.2, p. 72 |
| Running bill | Monthly; the Engineer checks it within 30 days | Bill on the printed form with measurements, QC test reports and instruction-book copies; contractor signs any corrections | GCC 39.1โ39.2, 40.1, pp. 68โ69 |
| Secured advance (up to 75% of material value) | With the monthly bill | Non-perishable, as per specification, at site, stored in measurable stacks, ownership shown, indemnity bond, not excessive | GCC 48.1, p. 73 |
| Variations and extra items | In the running bills | Item rate: quotation within 7 days of the Engineer's request. Lump sum: per Schedule S-II | GCC 38.1, p. 66; 37, p. 68; S-II, p. 117 |
| Compensation events | In the running bills | Must be claimed in the bills; claims not included are treated as waived | GCC 39.4, 41, pp. 69โ70 |
| Price adjustment (bitumen, cement, steel) | Monthly, with the bill | Not in the first 6 months (except bitumen in road works); lower price in extended time; no profit | GCC 44, p. 71; CD pp. 85โ86 |
| Refund of LD | Next payment certificate after EOT is granted | The completion date is extended after LD was paid | GCC 46.4, p. 72 |
| Refund of the deposit-at-call (arbitration) | After the award | In proportion to the amount awarded in the claimant's favour | GCC 25, p. 61 |
| Final payment | Within 56 days of a correct and complete final account | After the completion certificate | GCC 53, p. 74 |
| Retention: first 50% | 3 months after completion | Engineer certifies defects removed; final measurements recorded | GCC 45.2, p. 71 |
| Retention: balance 50% | After 1 year or the end of the DLP, whichever is later | All notified defects corrected | GCC 45.3, p. 71 |
| Performance security released | 28 days after the DLP ends | Validity ends then; extra PS for an unbalanced bid: 28 days after the completion certificate | GCC 49, p. 73 |
| EMD of an unsuccessful bidder | Within 28 days after the bid validity ends | The successful bidder's EMD stays in the retention | ITB 16.3โ16.4, p. 21 |
Money deducted or held back
| Deduction | When | How much | Clause |
|---|---|---|---|
| Retention (security deposit) | From every bill until completion | 5% of each payment; the EMD counts towards it | GCC 45.1, p. 71 |
| Mobilisation advance recovery | From the running bills | In proportion to the work completed, plus 9% interest a year; the BG reduces as the advance is repaid | GCC 47.1, 47.3, p. 72 |
| Secured advance adjustment | When the material is used in the work | The advance paid on that material is taken back | GCC 39.2, 48, pp. 69, 73 |
| Taxes at source (income tax TDS, GST TDS, cess, etc.) | From every bill | As per the law in force; rates are inclusive of taxes | GCC 39.2, 42.1, pp. 69โ70 |
| Liquidated damages | Late start (after 10 days), a missed milestone, late completion | Up to 1% of the contract amount a week, maximum 5% | GCC 46, pp. 71โ72 |
| Programme not updated | From the next payment certificate | The amount in the Contract Data, held until the updated programme is given | GCC 26.3, p. 62 |
| Third-party techno-financial audit | Works of Rs 1 crore and above | At the rate in the Department of Finance letters, on the total cost of work | GCC 31.2, p. 64 |
| Defect not corrected | After the time given in the defect notice | Twice the assessed cost of correcting it | GCC 34.1, p. 65 |
| As-built drawings / manuals not given | From the payments due (final bill) | Rs 10,000 or 1% of the contract amount, whichever is higher; due 15 days after completion | GCC 54.2, p. 74; CD p. 86 |
| Insurance premium paid by the Employer | If the contractor fails to insure | The premium paid | GCC 13, p. 58 |
| Labour law defaults, unpaid wages, fines | When the Employer has to pay them | The amount paid; can also come from the PS | GCC 10.3, p. 56; Labour Regulations, pp. 103โ108 |
| Excess payment or dues on any other contract | Any time | From any sum payable under this or any other contract with the Government | GCC 40.3, p. 69 |
| Earlier certified items | In a later certificate | The Engineer may exclude or reduce them in light of later information | GCC 39.5, p. 69 |
| Compensation on termination | On termination for the contractor's breach | 5% of the contract value; LD + compensation maximum 7.5% | GCC 56.1, p. 75 |
| EMD forfeited | Bid withdrawn, or the agreement or PS not given | The full EMD | ITB 16, p. 22 |
Running payments are only advances against the final payment; they are not acceptance of the work (GCC 40.5). Items with no rate entered are not paid (GCC 40.2).
Calculators
Pick a calculator. Each one shows the working step by step, has a Fill example button, a Download PDF button and a Know in detail guide in plain words.
๐ Your contract details: fill once, used in every calculator
Your entries in every calculator are saved only on this device, so you can come back later.
13. Tender timeline
Know in detail
How the dates are worked out
- Clarification requests must reach the Engineer more than 7 days before the deadline, so the last safe day is 8 days before.
- Pre-bid queries: 3 days before the meeting.
- Technical evaluation: within 21 working days of opening. Saturdays and Sundays are skipped here; gazetted holidays are not, so the real date may be a few days later.
- Clarification letter: usually within 10 days of opening; your reply within 7 days of the letter.
- Bid validity counts from the submission deadline; the LoA must come before it ends.
- EMD of unsuccessful bidders: within 28 days after validity ends.
Tip
- Upload a day early: the portal goes by its own server clock, and the department is not responsible for network problems (IFB 8).
1. Key dates and milestones
Know in detail
What the SBD says
- Performance security (5%) within 21 days of the LoA (ITB 30).
- Agreement signed within 28 days of the award (ITB 29.3).
- Work programme to the Engineer within 21 days (GCC 26.1).
- Work must start within 10 days of the acceptance letter, otherwise LD can be charged (GCC 46.1).
- Milestones: 10% of work at 25% of time, 30% at 50%, 65% at 75%, 100% at 100% (GCC 46.1).
- Half the retention is refunded 3 months after completion; the rest after 1 year or the end of the DLP, whichever is later (GCC 45).
- The PS must stay valid until 28 days after the DLP ends (GCC 49).
Worked example
Common mistakes
- Counting time from the agreement date: the Contract Data makes the allotment letter the start date.
- Letting the bank guarantee for the PS expire at completion: it must cover the DLP plus 28 days.
- Forgetting that the DLP is extended while defects are not corrected (GCC 33).
2. Liquidated damages (LD)
Know in detail
When LD applies (GCC 46.1)
- Work not started within 10 days of the acceptance letter.
- A milestone (10/30/65% of work at 25/50/75% of time) is missed.
- The whole work is not completed in time.
How much
- Up to 1% of the contract amount for each week of delay.
- The rate can be raised each time, up to 1% a week, but the total LD cannot be more than 5% of the contract value (46.2).
- The SE can reduce LD (46.3). If time is later extended, LD already taken is refunded (46.4).
- If part of the work is taken over, LD is reduced in proportion (46.6).
- Once LD reaches the maximum, the Employer can terminate the contract (GCC 55).
Worked example
Tips for contractors
- Apply for EOT within 30 days of each hindrance (GCC 27.1). Approved EOT means LD for that period is refunded.
- Keep a hindrance register signed by the JE/SDO; it is your proof.
- A part week is usually counted as a full week. Check the order.
3. Milestone progress check
Know in detail
The rule
- By 25% of the time: at least 10% of the work (by value).
- By 50%: 30%. By 75%: 65%. By 100%: the whole work.
- Missing a milestone allows LD of up to 1% a week (GCC 46.1), even though the final date has not come.
Where to get the figures
- Start date: the allotment letter date.
- Work done: the gross value of measured work in the running bills (before deductions).
Worked example
Tip
- If the delay was due to the department (site, drawings, payment), apply for EOT for the milestone as well, with the hindrance record.
4. Bid capacity
Know in detail
The formula (ITB 4.4)
- A = the highest value of civil works done in any one financial year of the last 5 years, updated to the bid year at 8% a year.
- N = the time for completion of this work, in years (18 months = 1.5).
- B = the value of existing commitments and ongoing works still to be done during the next N months (also updated).
- Bid capacity = A ร N ร 2 โ B. It must be at least the estimated cost.
Where to get the figures
- Yearly work values: a turnover certificate from a CA, or certificates from the engineers in charge.
- B: for each work in hand, the balance value that falls within the next N months as per its programme.
How the 8% updating is done here
- Each FY value is multiplied by 1 + 8% ร the years from the end of that FY (31 March) to the bid date. Ask the department if they count only whole years; this calculator shows the factor so you can check.
Worked example
5. Update a past value at 8%
Know in detail
Why update?
- Old values are brought to today's prices so they can be compared with the estimated cost. The BDS fixes 8% a year, simple (not compound).
- Updated value = Value ร (1 + 0.08 ร years).
Worked example
Note
- Some offices count whole years only. The calculator shows both the exact and the whole-year figure.
6. Eligibility check (works above Rs 10 crore)
Know in detail
Tests for works above Rs 10 crore
- Turnover: at least 40% of the estimated cost in any one of the last 3 FYs (updated at 8%).
- Similar works in the last 5 years (updated): one work of 80%, or two of 50% each, or three of 40% each of the estimated cost.
- Liquid assets / credit lines: the amount given in the BDS (about 3 months' peak cash flow), with an undertaking to invest 25% in cash and credit lines of 10% (ITB 4.2 B(f)).
- Bid capacity at least the estimated cost (use calculator 4).
Works up to Rs 10 crore
- Only valid PWD enlistment in the right class is needed (ITB 4.2 A / 4.3 A).
Common mistakes
- Using a work that is not "similar" as defined in the NIT.
- Counting a work completed more than 5 years before the bid date.
- Adding up two smaller works to make one 80% work: it doesn't count.
7. Securities, retention and advances
Know in detail
Performance security (ITB 30, GCC 49)
- 5% of the contract price within 21 days of the LoA, as a bank guarantee or FDR, valid until 28 days after the DLP.
- An extra PS may be asked for if the bid is unbalanced, more than 25% below the estimate (ITB 26.4).
Retention (GCC 45)
- 5% is deducted from each bill until 5% of the contract price is held. The EMD counts towards it.
- 50% is refunded 3 months after completion; the rest after 1 year or the end of the DLP (whichever is later), once defects are corrected.
Mobilisation advance (GCC 47)
- Up to 5% of the contract price excluding maintenance, against a bank guarantee of the same amount.
- Interest at 9% a year, recovered from the bills with the advance.
Secured advance (GCC 48)
- Up to 75% of the value of non-perishable materials brought to site for the work; recovered as the material is used.
Worked example
8. Price adjustment: bitumen, cement, steel (month by month)
What each box means and where to get the figure
Bitumen
- B0: the official retail price of bitumen at the Indian Oil (IOC) depot, Panipat, taken by the Department when it approved the bids. It is printed in your Contract Data (item 44).
- Bi: the official IOC Panipat retail price for the month. Take it from the IOC price circular for that month; your division office keeps these. If the price changed within the month, make two rows.
- Pb: the bitumen actually consumed in the work done that month, in MT.
Cement
- Rc: the cement rate per 50 kg bag taken by the Department while inviting bids, with the date it was fixed as a CSR rate. Both are printed in your Contract Data.
- C0: the All India Wholesale Price Index (WPI) for cement on the date Rc was fixed. It is an index number such as 127.7, not rupees. Enter the rate date and press Fill automatically.
- Ci: the same index for the month of work.
- Nc: the number of 50 kg bags actually consumed that month.
Steel
- Rs: the steel rate per MT taken by the Department while inviting bids, with its date (Contract Data).
- S0 and Si: the WPI for steel on the rate date and for the month of work. Index numbers, filled automatically.
- Qs: the steel actually consumed that month, in MT.
Dates
- Date of allotment: the date of allotment of the work. The first six months are counted from it.
- Original completion date: the intended completion date. Work after it is extended time.
- Price on the original completion date: for extended time the lower of this and the month's figure is used.
In the SBD: Vb = Pb ร (Bi โ B0)
More options (most users can skip these)
| Month | Pb: bitumen used (MT) | Bi: price for the month (Rs/MT) |
|---|
Know in detail
When PA is paid (GCC 44)
- For bitumen, cement and steel only, up or down with the market.
- Nothing is adjusted for work done in the first 6 months from the date of allotment. The only exception is bitumen in road works, which is adjusted from the start. In building works there is no exception.
- PA runs up to the intended completion date, or up to an extension granted by the Engineer. For work done in the extended time, the lower of the price on the intended completion date and the price for the month is used.
- Work executed under variations is left out; its rates are settled separately.
- No contractor's profit is added to PA.
Where to get the figures
- Bitumen: B0 is the IOC Panipat depot retail price printed in the Contract Data; Bi is the IOC Panipat price for the month. If the price changed within the month, split the month.
- Cement / steel: C0/S0 and Ci/Si are the All India Wholesale Price Index: C0/S0 on the date the rate Rc/Rs was fixed, Ci/Si for the month of work. Rc / Rs are the Department's rates printed in the Contract Data.
- Quantity: the quantity actually consumed in the work that month.
Worked example (cement)
9. Quantity variation and extra time
Know in detail
The rule (GCC 36)
- The rate can be revised only if both are true: the final quantity differs from the BOQ by more than 25%, and the change is worth more than 1% of the Initial Contract Price.
- The revised rate applies only to the quantity beyond 125% (or the shortfall below 75%). Up to 25% the BOQ rate applies.
- Without the Employer's approval, the total cannot exceed the ICP by more than 15%.
- Extra or changed work gets extra time in proportion to its value (GCC 36.1).
- For a variation the Engineer asks for, quote within 7 days (GCC 38.1).
Worked example
10. Payment on termination (contractor's breach)
Know in detail
When this applies
- The contract is terminated for a fundamental breach by the contractor, after 14 days' notice (GCC 55). Examples: work stopped for 28 days, delay reaching the maximum LD, a defect not corrected, the security not kept valid, corrupt practice.
The certificate (GCC 56.1)
- Value of work done โ advances received โ other recoveries โ TDS โ 5% of the contract value as compensation.
- LD + compensation together cannot exceed 7.5% of the contract value, or the amount available with the Engineer (retention, PS and dues), whichever is less.
- If the result is negative, the balance is recovered by encashing the PS.
Worked example
11. Dispute and arbitration deadlines
Know in detail
The steps (GCC 25)
- Refer the dispute to the Engineer in writing. He decides within 60 days.
- If not satisfied, give notice for arbitration within 60 days of the decision.
- The reference must be made within 120 days of the claim arising (6 months for final-bill matters), otherwise the claim may be barred.
- Deposit at call of 10% of the amount claimed with the reference.
- The award is to be given within 6 months.
Who is the arbitrator
- Claim up to Rs 5 crore: the Superintending Engineer of the circle.
- Rs 5 to 15 crore: another SE appointed by the Employer.
- Above Rs 15 crore: a 3-member tribunal.
Tips
- Keep proof of delivery of every letter; the deadlines run from the dates.
- Raise every claim in the running bills too: claims left out of the bills are treated as waived (GCC 39.4).
12. Running bill: what is paid and what is deducted
Know in detail
How a running bill is passed (GCC 39)
- Each month the contractor submits a bill on the printed form with the measurements, the quality-control test reports and copies of the instruction book.
- The Engineer checks it within 30 days and certifies the amount after deducting advances, retention, other recoveries and taxes at source. The contractor signs the corrections before payment.
- Include every claim (variations, compensation events) in the bills. Claims left out are treated as waived (39.4).
How this calculator works
- Retention: 5% of the total gross value so far, less what is already held (EMD + earlier retention). So the EMD is used up first.
- Mobilisation advance: recovered in proportion to the work done (this bill รท contract amount ร advance), never more than the balance, plus 9% a year interest on the balance for the months entered (GCC 47).
- Secured advance: up to 75% of the material at site is paid; the advance on material now built into the work is taken back.
- Taxes: enter the rates in force on the bill date. The calculator applies them to the gross value of work. Your office may use a different base; check with the accounts branch.
Common mistakes
- Taking retention again on the EMD part: the EMD is part of the 5%.
- Recovering the whole mobilisation advance from the first bills: the SBD says proportionate recovery.
- Forgetting to claim price adjustment every month.
FAQ: simple questions, tricky answers
Questions that look easy but are often answered wrongly at site and in the office. Each answer is from the SBD, with the clause.
Is retention money the same as the performance security?
Can LD ever be more than 5%?
If I get an extension of time later, do I get back the LD already deducted?
I missed a milestone but caught up later. Is the LD refunded automatically?
A BOQ quantity went up by 30%. Do I automatically get a new rate?
My DLP is 5 years. Do I get the second half of the retention after 1 year?
The first 50% of retention comes back 3 months after completion. Is that automatic?
Is the winning bidder's EMD returned like the others?
Can price adjustment reduce my payment?
Do I get price adjustment from the first month?
Is profit added on price adjustment?
Are the 21 days for the performance security working days?
Can I start the work before the agreement is signed?
I forgot to claim an extra item in the RA bills. Can I add it in the final bill?
My RA bill was passed. Does that mean the work is accepted?
The drawing and the BOQ say different things. Which one prevails?
Can I write 'subject to escalation' or another condition in my bid?
Can I give the performance security in cash or by cheque?
Who decides my EOT: the Executive Engineer or the SE?
Is the arbitrator someone outside the department?
Can the department recover money I owe on a different work from this bill?
Is interest paid on my EMD or retention money?
Does the secured advance carry interest like the mobilisation advance?
Is the DLP counted from the start date or the completion date?
My bid is 26% below the estimate. Is there any catch?
The site was handed over late. Will I be paid for the idle time?
Can I sublet 30% of the work with the EE's permission?
A defect was not corrected and repair is assessed at Rs 50,000. How much will be recovered?
If I don't give the as-built drawings, how much is held back?
If my enlistment is valid on the bid date but expires soon after, is that okay?
Didn't find your question? Ask here
Send your question about the Punjab PWD SBD. We read every question and add the useful ones to this page.
Related guides
Based on the Standard Bidding Document for Procurement of Works, Government of Punjab, PWD (B&R) Branch, dated 12-12-2025. This is a study aid, not the contract. Where this page and your agreement differ, the agreement prevails.