Also in PMGSY: eMARG Guide · PMGSY SBD Helper
e-MB & e-Billing Guide for PMGSY (OMMAS)
Electronic Measurement Book and e-Billing in OMMAS, step by step: BoQ, logins, opening balances, recording and checking measurements, RA bills, quantity deviation and reports. Who does what, which menu to click, and what to do when a work doesn’t show up.
1I am
2I want to
Where is my file stuck?
Pick the status you see in OMMAS. You’ll see who has to act next and what they must click.
e-MB: measurement chain
JErecords, finalisesFINALIZED BY JE
Contractoracceptance formforwards
AE50% checkforwards to EE
EE10% checkMB approved
e-Billing: RA bill chain (OTP at every step)
JEmakes billDRAFT → FORWARDED TO AE
AEreviewsFORWARDED TO EE
EEforwardsSent to authorized signatory
Accountantconsent—
EEApprove BillApproved by EE
Any level can send back down, with a compulsory remark.
The full sequence for one work
| # | Step | Who | When | If missed / status |
|---|
From the MoRD D.O. No. NRRDA-P010(18)/1/2025-(P-I) dated 12 August 2026 (Joint Secretary, RC) to all States/UTs and SRRDAs.
14.08.2026e-MB & e-Billing roll-out in OMMAS
13.08.2026VC training (States/UTs whose EC is held, compliance awaited)
17.08.2026VC training by NRIDA & C-DAC (per Annexure)
30.08.2026Cut-off: balance quantities of ongoing works worked out as on this date
What the D.O. requires
- One BoQ from DPR → Technical Sanction → Tender → Execution → e-MB → e-Billing. Quantities finalised at DPR stage stay frozen.
- New works: BoQ made and finalised in OMMAS at DPR stage, before EC compliance; SBD and BoQ pushed to GePNIC from OMMAS.
- Ongoing works: balance quantities (sanctioned minus executed as on 30.08.2026) entered in the standard BoQ format in OMMAS; all later measurements in e-MB.
- Each State/UT to name a nodal officer for e-MB and e-Billing.
- States are responsible for correct BoQ and quantities, training attendance, recording measurements in e-MB and making bills only through e-Billing. Technical problems go to NRIDA.
What’s new in User Manual v1.2 (over v1.1)
- Revise BOQ after MoRD approval, with BoQ versions
- 50% check by AE and 10% check by EE before measurements are approved
- Agreement Details: award % excess/less, with manual entry if GePNIC has no data
- Section planning and stage passing as e-MB pre-requisites
- Creating the Quality First-tier PIU login from ITNO
Written by Help The Engineer Team
Review: being checked by senior engineers. Spotted an error? Tell us on WhatsApp.
Based on the NRIDA / C-DAC “User Manual for e-MB, OMMAS-PMGSY” (Version 1.2) and the MoRD D.O. dated 12.08.2026. Menu names and steps can change: always follow the current NRIDA instructions and OMMAS screens. This is not an official NRIDA or MoRD page.