Site Calculators

🧮
Civil Engineering Calculators
Steel • Concrete • Bricks • Shuttering • Land • Cost
22 toolsm / ftFree
📏 Units
mm sizes stay in mm

🔩 TMT Bar Weight Calculator

Weight (kg/m) = D² ÷ 162  (D in mm)
Length of one barDiameter
What to fill
Example: 100 bars of 12 mm, each 12 m long. Pick Bar diameter 12, then fill Length of one bar 12 and Number of bars 100. To go the other way, fill the total weight in kg in the last box and it gives the number of bars.
Dia (mm)kg per metrekg per 12 m barBars per tonne (12 m)

⚖️ Metal Weight Calculator (Steel, Aluminium, SS…)

Weight = cross-section area × length × density
LengthWidthThickness = sheet thicknessWidthThicknessDiameterSideOutside diameterWall thicknessOutside sideWall thicknessOutside widthOutside heightWall thicknessLeg ALeg BThicknessDepth hFlange width bWeb thicknessFlange thicknessDepth hFlange width bWeb thicknessFlange thickness
What to fill
All sizes are in mm. Length is the length of the piece. Quantity is the number of pieces.

Channels and I-beams are worked out from plate dimensions (no root fillets), so they are approximate. For standard ISMB, ISMC and ISA sections, use the weights in IS 808. Square and rectangular hollow sections in steel are worked out with rounded corners, so the result matches the IS 4923 tables.

🏗️ Concrete Quantity Calculator (Nominal Mix)

Dry volume = wet volume × 1.54  |  1 bag cement = 50 kg = 0.0347 m³
LengthWidthThickness = depth
What to fill
Example: a slab 5 m long, 4 m wide and 125 mm thick. Pick the grade, then fill Length 5, Width 4 and Thickness 0.125. Thickness is typed in metres: 125 mm is 0.125. Leave the water-cement ratio at 0.5 unless you know it.

Nominal mixes as per IS 456 (Table 9) up to M20. *M25 (1:1:2) is a common site practice; for M25 and above, IS 456 recommends a design mix (IS 10262). Add 2–5% for wastage.

🧱 Brickwork / Block Calculator

Bricks = wall volume ÷ volume of one brick with mortar
OpeningWall lengthWall height
What to fill
Example: a wall 10 m long and 3 m high, one brick (230 mm) thick, with a door of 2 sq m. Fill Wall length 10 and Wall height 3, pick the thickness, and fill Openings 2. Brick size is typed as length, width and height in mm with the letter x between them.

Common sizes: conventional brick 230×110×75 mm, modular brick 190×90×90 mm, AAC block 600×200×(100–200) mm with 3–5 mm adhesive joints.

🪣 Plaster Calculator

Dry mortar = area × thickness × 1.33 (allows for joints, voids and wastage)
What to fill
Example: a wall 10 m long and 3 m high, plastered on one side, is 10 times 3, that is 30 sq m. Fill Plaster area 30, then pick the thickness (12 mm for inside walls) and the mix.

🔲 Tiles & Flooring Calculator

Tiles = floor area ÷ area of one tile + wastage
Room lengthRoom width
What to fill
Example: a room 4 m long and 3.5 m wide. Fill Room length 4 and Room width 3.5, pick the tile size, and fill how many tiles come in one box (printed on the box).

🎨 Paint Calculator

Paint (litres) = area × coats ÷ coverage per litre
What to fill
Example: walls and ceiling add up to 150 sq m, doors and windows are 10 sq m, and you want 2 coats. Fill 150, 10 and 2. Coverage is printed on the paint tin; change the two coverage boxes only if your tin says something different.

Coverage depends on the brand and surface. Check the paint tin; rough surfaces need more paint.

🔗 Development Length & Lap Length (IS 456)

Ld = φ × 0.87 fy ÷ (4 τbd)
Lap length
What to fill
Example: 16 mm bars of Fe 500 steel in M25 concrete. Pick the bar diameter, the steel grade and the concrete grade. There is nothing to type.

τbd for deformed (TMT) bars = plain-bar value × 1.6; in compression, increased by a further 25% (IS 456, Cl. 26.2.1.1). Lap in flexural tension = greater of Ld and 30φ; lap in compression = greater of Ld (compression) and 24φ (Cl. 26.2.5.1). Avoid laps at points of maximum stress and stagger them.

⛏️ Earthwork / Excavation Calculator

Volume = L × D × (B + n·D)  (n = side slope, horizontal : 1 vertical)
Bottom widthDepthslopen
What to fill
Example: a trench 20 m long, 1 m wide at the bottom and 1.5 m deep. Fill Length 20, Bottom width 1 and Depth 1.5. Side slope n is how far each side goes out for every 1 of depth: 0 for vertical sides, 0.5 means 0.5 m out for every 1 m down, and 1 is a 45 degree side.

💧 Water Tank Capacity Calculator

1 m³ = 1000 litres
LengthWater depthWidth = other side
What to fill
Example: a tank 2.5 m long and 2 m wide holding 1.5 m of water. Pick Rectangular, then fill Length 2.5, Width 2 and Water depth 1.5. For a round tank pick Circular and fill the diameter. The last three boxes check if the tank is enough for your family.

135 litres per person per day is the usual domestic demand for cities with full flushing systems (NBC / IS 1172). Leave about 150 mm free board above the water level.

📐 Steel Quantity in RCC

Steel (kg) = concrete volume × steel % ÷ 100 × 7850
What to fill
Quick estimate (first box): pick the element, then fill its length, width and depth in metres and how many there are. Example: one slab 5 m by 4 m and 125 mm thick is Length 5, Width 4, Depth 0.125. Slab bars (second box): fill the slab size, the bar diameters and the spacing between bars in mm.

Slab mesh (exact bars)

Steel % values are typical thumb rules for estimating only. Actual steel comes from the structural drawings / bar bending schedule. The slab mesh assumes main bars run along the shorter span; add hooks, cranks and laps as per the drawing.

Need exact cutting lengths and a full bar bending schedule? Use the BBS Calculator →

🧪 Concrete Mix Design (M20–M40)

Full IS 10262:2019 mix design calculator

M20 to M40 • exposure checks as per IS 456 • sand moisture & absorption corrections • admixture • per-bag quantities • step-by-step working

Open Mix Design Calculator →

Opens on its own page. Always confirm the design with trial mixes and cube tests before use on site.

🏛️ Footing & Column Concrete

Sloped part = h/3 × (A1 + A2 + √(A1 × A2))
Base lengthBase depthSlope heightColumn
What to fill
Example: a footing 1.5 m by 1.5 m with a flat base 0.3 m deep, a sloped part 0.2 m high that narrows to 0.5 m by 0.5 m, and a 300 by 300 mm column 3 m high. Fill the boxes in that order. If the footing has no slope, put 0 for Sloped part height. A size with two numbers is typed with the letter x between them.

🧊 Cube Compressive Strength

Strength (N/mm²) = load (N) ÷ area (mm²)
What to fill
Example: three cubes broke at 245, 252 and 238 kN at 28 days. Pick the cube type, the grade and the age, then fill the three loads exactly as read from the testing machine, in kN.

Cement: minimum strength as per IS 269 / IS 1489. Concrete: % of fck shown against typical strength gain only; acceptance of concrete is judged as per IS 456 (Cl. 16) on groups of results.

🪵 Shuttering Area & Removal Dates

A. Shuttering area

What to fill
Example: one slab 5 m by 4 m, four beams each 4.5 m long and 230 by 450 mm, and four columns 300 by 300 mm and 3 m high. Fill the slab, beam and column boxes. For removal dates, set the date and time concreting finished and pick the slab and beam spans.

B. When to remove formwork (IS 456, Cl. 11.3.1)

Times are for OPC concrete and ordinary weather (above 15 °C) as per IS 456. For slow-hardening cements (PPC, PSC) or cold weather, keep the formwork longer, as decided by the engineer-in-charge. Re-prop slabs and beams if loads come early.

🪜 Staircase Calculator

Risers = floor height ÷ riser  |  comfort check: 2R + T ≈ 550–700 mm
TreadRiser
What to fill
Example: floor to floor is 3 m. Fill Floor-to-floor height 3, Maximum riser 170, Tread 270 and Stair width 1.0, then pick 1 or 2 flights. Riser is the height of one step. Tread is the flat part you step on.

NBC 2016 (residential): riser not more than 190 mm, tread not less than 250 mm, clear width at least 1.0 m (0.9 m for low-rise houses). Concrete shown excludes landings.

📏 Slope & Gradient Converter

Slope % = rise ÷ run × 100  |  angle = tan⁻¹(rise ÷ run)
Run (horizontal length)Rise
What to fill
Example: a drain laid at 1 in 40 over 10 m. Pick “1 in n”, fill Value 40 and Horizontal length 10, and it gives the fall.

Typical values: road camber 2–2.5% (bituminous), roof drainage 1 in 100 to 1 in 120, ramps for wheelchairs 1 in 12, drains 1 in 300 to 1 in 1000.

🌾 Land Area Converter (Acre – Kanal – Marla – Gaj – Bigha)

1 Acre = 8 Kanal = 160 Marla = 4840 Gaj = 43,560 sq ft
What to fill
Example: 1 acre 2 kanal 5 marla. Fill Acre 1, Kanal 2 and Marla 5. To convert a single figure such as 5000 sq ft, put 0 in the first three boxes, fill 5000 in “plus another value” and pick Sq ft.

Marla = 272.25 sq ft (Karam of 66 inches), as used in Punjab and Haryana revenue records. Bigha and Biswa differ from state to state; Punjab values are used here (1 Bigha = 9,075 sq ft).

🔄 Engineering Unit Converter

What to fill
Example: 25 feet into metres. Pick Length, fill Value 25, then pick the unit you have in From and the unit you want in To.

🏠 House Construction Cost & Materials

Cost = built-up area × rate per sq ft
What to fill
Example: a house of 1000 sq ft at Rs 2000 per sq ft. Switch Units to Feet to type the area in sq ft, then fill the area and the rate.

Material quantities are common thumb rules for an RCC framed house (per sq ft of built-up area): cement 0.4 bag, sand 1.816 cft, aggregate 1.35 cft, steel 4 kg, bricks 8 nos, paint 0.18 litre, tiles 1.3 sq ft. The cost split is a typical average. Rates vary by city, design and finish; use this only as a first estimate.

📋 Unit Weights of Common Materials

MaterialUnit weight
Reinforced cement concrete (RCC)25 kN/m³ (2500 kg/m³)
Plain cement concrete (PCC)24 kN/m³ (2400 kg/m³)
Brick masonryabout 19–20 kN/m³
Steel78.5 kN/m³ (7850 kg/m³)
Aluminium27 kN/m³ (2700 kg/m³)
Cement (loose)14.4 kN/m³ (1440 kg/m³)
Sand (dry, loose)about 15–16 kN/m³
Coarse aggregate (loose)about 15–16 kN/m³
Water9.81 kN/m³ (1000 kg/m³)
Glassabout 25 kN/m³

Typical values; for design, use IS 875 (Part 1).

⚠️ Note: these calculators give quick estimates for planning and checking. For final quantities, designs and payments, follow the drawings, the relevant IS code and your contract.