Updated November 2026 · Sources: BIS handbook SP 27:1987 and IS 1200
Quick answer: measure the finished work net, book length, breadth and height in that order, and deduct an opening only when it is larger than the limit for that trade: 0.1 sq m for concrete and brickwork, 0.4 sq m for formwork and 0.5 sq m for plaster.
Most beginners learn rates first and measurement rules much later, usually after an audit objection or a dispute with a contractor. This guide gives the rules early, in plain words, with two worked examples, seven diagrams and a self-test.
- Why measurement rules matter
- What IS 1200 and SP 27 are
- Six general rules to learn first
- Trade-by-trade quick guide
- Common mistakes beginners make
- Worked example 1: plaster
- Worked example 2: brick wall and column
- Checklist before you submit
- Where these trades sit in Punjab CSR 2020
- Test yourself
- What has changed since 1987
- Terms you will meet
Why measurement rules matter
An estimate is only as good as its measurements, and measurement follows written rules, not personal habit. Two engineers measuring the same wall can get two different quantities. One deducts every small opening, the other deducts none. One measures a column up to the top of the slab, the other stops at the underside.
Each small difference repeats across a whole building and becomes a real difference in cost. When the estimate, the bill of quantities and the final bill all follow the same method, the quantities agree and payments are easier to defend.
What IS 1200 and SP 27 are
- IS 1200 is the Indian Standard for the method of measurement of building and civil engineering works. It is issued in separate parts, one for each trade, such as earthwork, concrete or brickwork.
- SP 27:1987 is the BIS Handbook of Method of Measurement of Building Works. It gathers the IS 1200 rules into one book of 22 sections, from general rules and materials to roadwork.
- Your contract decides which rules apply. Department specifications (CPWD, state PWD) are mostly based on IS 1200 but can differ in details.
Six general rules to learn first
These apply to almost every trade, so learn them before any trade-specific rule.
- Measure net, as fixed in place. Measure the finished work, not the material bought. Waste, cutting, handling and scaffolding are part of the rate, not extra quantity.
- Book dimensions in a fixed order. Always write length, then breadth or width, then height, depth or thickness.
- Round as the handbook says. Dimensions to the nearest 0.01 m, areas to 0.01 sq m and volumes to 0.01 cu m. Steelwork is finer: dimensions to 0.001 m, and reinforcement lengths to 0.005 m.
- Describe the item fully. The bill of quantities must state the material and workmanship clearly, so the rate and the quantity refer to the same thing.
- Measure in stages where height or depth changes the cost. Work below and above ground or datum level is kept separate for trades such as concrete, brickwork and stone masonry.
- Keep difficult conditions separate. Work in or under water, in liquid mud, in foul positions or under tides is measured as its own item because it costs more.
Trade-by-trade quick guide
The table lists the unit and the rules beginners most often get wrong. Section numbers refer to SP 27:1987.
| Trade (SP 27 section) | Unit | Rules to remember |
|---|---|---|
| Earthwork (3) | cu m | Depth is measured in stages of 1.5 m. Lead is taken along the shortest practicable route, in 50 m units up to 250 m. Excavation up to 30 cm deep over a wide area is surface excavation, in sq m. |
| Concrete (5) | cu m | No deduction for the volume of reinforcement or for openings up to 0.1 sq m. Columns run from the top of the column base to the underside of the slab, then slab top to the underside of the next slab. |
| Brickwork (6) | cu m | No deduction for openings up to 0.1 sq m or for ends of beams, lintels and joists up to 0.1 sq m in section. Wall thickness is taken in multiples of half a brick. |
| Formwork (8) | sq m | Measure the area in contact with concrete. No deduction for openings up to 0.4 sq m. |
| Steel and iron work (10) | kg or tonne | Reinforcement is measured by weight and includes cutting, hooks and bending. For welded structures, add nothing for weld metal. For riveted structures, add 2.5 percent for rivet heads. |
| Plastering (16) | sq m | Openings up to 0.5 sq m: no deduction. From 0.5 to 3 sq m: deduct one face only when both faces have the same plaster. Above 3 sq m: deduct the opening and measure jambs, soffits and sills. |
| Painting (18) | sq m | Doors and windows are measured flat and multiplied by a factor, for example 1.30 per side for a panelled door and 1.20 per side for a flush door. |
The usual reasoning behind the small-opening rules is that the extra labour of forming a small opening roughly balances the material saved, so it is ignored.
A 4.5 m deep trench gives three entries, one per stage, not one entry for the full depth.
Common mistakes beginners make
Most wrong deductions come from carrying one trade's limit into another.
- Deducting every opening. Small openings are not deducted. Check the limit for the trade.
- Using one limit for all trades. The plaster limits do not apply to brickwork, and the brickwork limit does not apply to formwork.
- Deducting steel from concrete. The volume of reinforcement is never deducted from the concrete quantity.
- Measuring columns through the slab. The column stops at the underside of the slab, so the junction is not counted twice.
- Measuring lead along the route the truck took. Lead is the shortest practicable route, even if the actual route was longer.
- Adding wastage to the quantity. Measurement is net. Wastage belongs in the rate analysis.
- Mixing above and below ground level. Keep them as separate entries where the handbook asks for stages.
Worked example 1: plaster on a wall with three openings
A wall 4.00 m long and 3.00 m high is plastered on both faces with the same plaster. It has a door, a window and a ventilator.
| Opening | Size (m) | Area (sq m) | Rule | Deduction (sq m) |
|---|---|---|---|---|
| Door | 1.00 x 2.10 | 2.10 | 0.5 to 3 sq m: one face only | 2.10 |
| Window | 1.50 x 1.20 | 1.80 | 0.5 to 3 sq m: one face only | 1.80 |
| Ventilator | 0.60 x 0.60 | 0.36 | Up to 0.5 sq m: none | 0.00 |
Total deduction ............. 2.10 + 1.80 = 3.90 sq m
Plaster to be paid .......... 24.00 - 3.90 = 20.10 sq m
No jambs, soffits or sills are added for these openings. A beginner who deducts all three openings on both faces gets 15.48 sq m, which is 4.62 sq m short on one small wall.
How the entry looks on a measurement sheet
| Description | No. | L (m) | B (m) | H (m) | Quantity (sq m) |
|---|---|---|---|---|---|
| Plaster to wall, both faces | 2 | 4.00 | - | 3.00 | 24.00 |
| Deduct door, one face | 1 | 1.00 | - | 2.10 | -2.10 |
| Deduct window, one face | 1 | 1.50 | - | 1.20 | -1.80 |
| Ventilator 0.36 sq m | - | - | - | - | no deduction |
| Net plaster | 20.10 |
Writing the ventilator as a line with "no deduction" shows the checker that you saw it and applied the rule.
Worked example 2: a brick wall and a concrete column
Brick wall. A one-brick wall (0.23 m thick) is 4.00 m long and 3.00 m high. It has a door 1.00 m x 2.10 m and a pipe hole 0.25 m x 0.25 m.
| Item | Working | Quantity (cu m) |
|---|---|---|
| Gross brickwork | 4.00 x 0.23 x 3.00 | 2.76 |
| Deduct door (2.10 sq m, above 0.1 sq m) | 1.00 x 0.23 x 2.10 | -0.48 |
| Pipe hole (0.06 sq m, up to 0.1 sq m) | no deduction | 0.00 |
| Net brickwork | 2.28 |
The same door that was deducted from only one face of plaster is deducted in full from brickwork. The trade decides the rule, not the opening.
Concrete column. A column 0.30 m x 0.45 m stands on its base. The underside of the first floor slab is 3.20 m above the top of the base, and the slab is 0.15 m thick.
| Item | Working | Quantity (cu m) |
|---|---|---|
| Column concrete | 0.30 x 0.45 x 3.20 | 0.43 |
| Volume of reinforcement inside it | no deduction | 0.00 |
| Slab thickness of 0.15 m | measured with the slab, not added here | 0.00 |
| Column concrete | 0.43 |
Checklist before you submit a measurement
- The unit matches the item in the schedule of rates.
- Dimensions are booked as length, breadth, height.
- Dimensions are to 0.01 m, and areas and volumes to two decimals.
- Each opening is checked against the limit for that trade.
- Nothing is counted twice at junctions of columns, beams and slabs.
- Work below and above ground level is kept separate where required.
- The description says what is included in the item.
- The method matches the contract and the department specification.
Where these trades sit in Punjab CSR 2020
If you work in Punjab, the quantity you measure is priced from the Common Schedule of Rates. Each trade above has its own chapter.
| Trade | CSR 2020 chapter |
|---|---|
| Carriage of materials (lead) | Chapter 5 |
| Earthwork | Chapter 6 |
| Centring and shuttering (formwork) | Chapter 9 |
| Concrete | Chapter 10 |
| Brickwork | Chapter 11 |
| Plastering and pointing | Chapter 15 |
| White washing, distempering and painting | Chapter 16 |
| Steel and iron work | Chapter 18 |
Read the notes at the head of the chapter before measuring. Where a chapter note or an A&C slip gives its own rule for an item, follow that for work priced from the CSR.
Test yourself
Answer first, then open each question to check.
1. A ventilator of 0.45 sq m sits in a plastered wall. Is it deducted from the plaster?
No. It is within the 0.5 sq m limit for plaster.
2. The same wall is one brick thick. Is the ventilator deducted from the brickwork?
Yes. It is above the 0.1 sq m limit for brickwork.
3. A column holds 60 kg of reinforcement. Is that volume deducted from the concrete?
No. The volume of reinforcement is never deducted.
4. A slab has a 0.30 sq m cut-out. Is it deducted from the formwork?
No. It is within the 0.4 sq m limit for formwork.
5. A trench is 2.40 m deep. How many depth entries do you book?
Two: 0 to 1.5 m, and 1.5 to 2.4 m.
6. The truck ran 400 m to the dump, but a 220 m route was practicable. Which lead do you take?
220 m, the shortest practicable route.
What has changed since 1987
The handbook itself has not been revised: SP 27:1987 (first revision) is still the edition BIS lists. What has moved is IS 1200, the standard behind it. The handbook's own foreword says that for contracts you should refer to the relevant IS 1200 parts.
| IS 1200 part | Trade | Edition in force | What it means for you |
|---|---|---|---|
| Part 1 | Earthwork | 1992 (fourth revision), newer than the handbook | Check earthwork rules against this part, not SP 27 |
| Part 5 | Formwork | 2013 (fourth revision) | Check formwork rules against this part |
| Part 7 | Hardware | 2013 (third revision) | Revised after the handbook |
| Part 27 | Earthwork by mechanical appliances | 2024 (second revision) | Not covered in the handbook's building sections |
| Part 2 | Concrete works | 1974 with two amendments, reaffirmed 2022 | Same base edition as the handbook; a fourth revision is in draft |
| Part 15 | Painting and polishing | 1987, amended in 2002 | Read the amendment along with the part |
BIS also circulated draft fourth revisions of Part 3 (brickwork) and Part 12 (plastering and pointing) for comments in 2025. Until a revision is published, the existing part stays in force.
Source for editions: BIS list of published standards, Methods of Measurement committee (CED 44), checked November 2026. Editions change, so confirm on the BIS site before quoting a clause in a contract or a reply to audit.
Terms you will meet
- Net measurement: the finished work as fixed in place, without wastage.
- Lead: the horizontal distance material is carried.
- Lift: the height or depth through which material is raised.
- Running metre: measured by length only, such as a skirting or a pipe.
- Enumerated: counted in numbers, such as fittings.
- Extra-over: an additional rate paid on top of the main item for a harder part of the same work.
- Girth: the distance measured around a surface, following its profile.
Key takeaways
- Measure net, and book length x breadth x height every time.
- Opening limits: 0.1 sq m concrete and brickwork, 0.4 sq m formwork, 0.5 sq m plaster.
- Plaster openings from 0.5 to 3 sq m come off one face only when both faces have the same plaster.
- Columns stop at the underside of the slab; reinforcement volume is never deducted.
- SP 27 teaches the method; the current IS 1200 part and your contract decide the quantity.
References: Bureau of Indian Standards, SP 27:1987, Handbook of Method of Measurement of Building Works (First Revision); IS 1200, Method of Measurement of Building and Civil Engineering Works (relevant parts). This article explains the rules in our own words. Refer to the handbook, the current IS 1200 parts and your contract for the exact wording.